Southern Water Sewer Upgrade Work Commences May 19 2025
Please see listed below the initial schedule of work and supporting maps. Clancy advise that as with all projects, these timescales can be subject to changes.
- Phase 1a - Station Road
19 May - End of June (~ 5 weeks)
- Phase 1b - The Square
End of June - Mid July (~ 3 weeks)
- Phase 2 - Water Lane from High Street to Cumberland Road
Mid July to September (~ 8 weeks)
- Phase 3 - Water Lane from Cumberland Road to Dappers Lane
September to December (~ 16 weeks)
If you have any questions regarding these works please contact Southern Water Customer Service on 0330 303 0368. Just tell us you’re calling about Capital Projects, with Project Reference Number (PRN) 760041 so we can help you more quickly