Southern Water Sewer Upgrade Work Commences May 19 2025

FB_road_closure_1a___1b.png
fb_road_closure_phase_2.png
FB_Road_Closure_Phase_3.png
FB_Wastewater_Pipeline_Route.png

Please see listed below the initial schedule of work and supporting maps. Clancy advise that as with all projects, these timescales can be subject to changes.

  • Phase 1a - Station Road
    19 May - End of June (~ 5 weeks)

 

  • Phase 1b - The Square
    End of June - Mid July (~ 3 weeks)

 

  • Phase 2 - Water Lane from High Street to Cumberland Road

          Mid July to September (~ 8 weeks)

 

  • Phase 3 - Water Lane from Cumberland Road to Dappers Lane

          September to December (~ 16 weeks)

If you have any questions regarding these works please contact Southern Water Customer Service on 0330 303 0368. Just tell us you’re calling about Capital Projects, with Project Reference Number (PRN) 760041 so we can help you more quickly